When a metal plating works was discovered to have been contaminating
local residents' gardens, the environmental health department
had to embark on a sensitive clean up operation. Charles Bradfield
and Joanne Ellis look at the lessons learned.
Part IIA of the Environmental Protection Act 1990 (EPA) has been
in place for over a year now.1 As local authorities start to implement
their strategies for identifying contaminated land, candidate sites
will be identified and it is likely that these will include a number
of existing residential developments. Any supplementary assessment
will require extremely sensitive handling with respect to the media
and local residents. Recent enforcement action taken by Wokingham
District Council under the pre-existing legal framework of statutory
nuisance provides key practical lessons learned and a basis for
comment on application of the new contaminated land regime.
INITIAL COMPLAINT
In January 1998, Wokingham DC received a complaint from local residents
who were concerned that an adjacent metal plating works had contaminated
their gardens. Soil samples were taken from two gardens of the residents
concerned and these indicated the presence of elevated levels of
cadmium to a maximum concentration of 88mg/kg. This level is significantly
higher than the ICRCL trigger level of 3mg/kg and the Dutch standard
of 12mg/kg.2 3 The Berkshire Health Authority was consulted and
it was agreed as a precautionary approach that the occupants of
the dwellings adjacent to the works should be advised not to eat
any home grown vegetables or let young children play directly with
the garden soil. Letters to this effect were sent to all properties
whose gardens backed on to the metal plating shop, as well as the
original two properties where the samples were taken. Following
receipt of these letters, a number of residents contacted the local
media and pressure was on to resolve the matter as soon as possible.
Tenders were invited for an assessment of the level and extent of
contamination in all 12 surrounding residential properties and the
plating works itself. Applied Environmental Research Centre (AERC)
was commissioned to carry out the assessment in May 1998.
RISK ASSESSMENT
A phased investigation was carried out to establish the extent and
level of contamination and an assessment of the associated risk
to residents of the adjoining properties. The investigation found
high levels of heavy metal contamination, particularly cadmium up
to 755mg/kg on the factory site and 550mg/kg in the neighbouring
gardens. The assessment concentrated on cadmium as the principal
hazard, as other elevated concentrations were proportionately low
and generally associated with cadmium. In the absence of any mandatory
guidance, and as the UK ICRCL guidance has no action level for cadmium,
the Dutch criteria were used to assess risk. The Dutch standards
give intervention values (IV) for soil concentrations calculated
for a standard soil - for cadmium the IV is 12mg/kg. Site specific
IV's were recalculated taking into account the percentage clay and
organic matter which affects the availability of cadmium. Based
on this, IV's for cadmium were taken as: topsoil 10mg/kg and subsoil/made
ground 8mg/kg. In addition, the depth of contamination, the mobility
of cadmium within the soil and analysis of edible vegetables collected
from residents' gardens were also used to assess risk. Analysis
of vegetable samples taken from the gardens found cadmium levels
in some vegetables up to 0.57mg/kg. The maximum cadmium concentration
in food recommended by the European Commission is 0.1mg/kg.4
LIAISON WITH HEALTH AUTHORITY
The risk assessment concluded that there was a moderate to high
risk in four of the adjacent properties, with a level of contamination
that was potentially injurious to the health, but a low risk in
the rest. The results of the investigation were discussed with Berkshire
Health Authority and the Guys and St Thomas Toxicology Unit. In
two of the worst affected properties, residents had lived there
for many years and had eaten a significant amount of home grown
vegetables. As cadmium is a bio-accumulator, it was decided to collect
blood and urine samples to establish whether there was any accumulation
of cadmium within their bodies. Results showed no build up of cadmium.
CONSIDERATION OF ENFORCEMENT ACTION
As the new contaminated land regime was not yet in force, and there
was no certainty as to when it may be, the serving of an abatement
notice to require the remediation of the land was considered. To
do this, the person responsible for the nuisance had to be identified
and if this could not be established then any action would have
to be taken against each individual owner. Following discussions
with Counsel, it was considered necessary to carry out further investigation
to confirm that the source of contamination was the plating site
and to demonstrate that there was ongoing migration of the contaminant
from the plating site to the gardens. For this purpose the history
of the site was researched further and additional soil, water and
vegetable samples were taken. The plating works had closed shortly
after the initial investigation (although not as a consequence of
the council's actions) but metal plating had taken place on the
site since 1938, with houses being constructed after the works in
the 1960s. The investigation showed the works and houses had been
built on filled land which potentially could be a source of contamination.
It was also a possibility that the contamination could have been
caused by the dumping of waste from the works prior to construction
of the houses. The integrity of the underground settlement tanks
was also tested and found to be leaking at a rate of 0.117 litres/hour
(12.8 litres over five days) which would have been a source of contamination
over the years. Although, as the plant had now shut down, this would
not be a contributory factor once the tanks had been emptied. Planning
records showed that waste from the plant had gone to a soakaway
in the east of the site until the late 1960s and this would have
been a significant source of contamination. In order to demonstrate
that the contamination had migrated from the works site into the
gardens, and that there was ongoing migration across the boundary,
further soil analysis and groundwater sampling was carried out to
show that cadmium was leaching into the groundwater and hence in
a mobile form. From leachate and soil fractionation tests it was
concluded that cadmium was mobile and had a high potential for plant
uptake; the raised cadmium levels found in the vegetable samples
backed this up. The presence of other contaminants typically associated
with electroplating within the adjoining gardens also indicated
that the cadmium contamination had originated from the electroplating
works.5 Contaminated land assessments carried out on a former petrol
storage depot adjacent to the site showed that groundwater movement
was in a north to south-east direction. The pattern of contamination
found correlated with this.
SERVING NOTICE
It was concluded that it was highly probable that the source of
cadmium was from the metal plating works and that there was a potential
for the ongoing migration into neighbouring gardens. Hence, it was
decided to serve an abatement notice under Section 80 of the Environmental
Protection Act 1990 requiring the owners of the site, as the persons
responsible for the contamination, to remediate the four affected
gardens. They were also required to remediate the factory site itself,
as there was a significant pool of contamination that could recontaminate
the gardens. AERC prepared a remediation method statement that formed
the schedule of works to the notice. It was considered that, as
residential gardens were affected, "dig and dump" was the only feasible
method of decontamination. Containment methods were considered for
the factory site but would not have been practicable. As the notice
required works to be carried out on land which was not owned by
the person responsible, legal consents were obtained from the owners
of the four affected houses. This enabled any contractors to enter
the properties for the purpose of carrying out the works required
by the notice. The notice gave three months for the works to be
completed.
WORKS IN DEFAULT
The owners of the factory site were trying to sell the property
to a developer who would then carry out the remediation works prior
to developing it for residential use. Although there were a number
of developers who had shown an interest in the site by the end of
the specified time, the sale of the land, or the remediation of
the site, did not appear imminent. Due to the potential cost of
remediation, the decision to carry out works in default was put
to the Environmental Services Committee and it was decided to proceed
with the works. Supplementary credit approval had been provisionally
agreed by the then DETR prior to this committee and that assisted
members in their decision, especially when considering the financial
liabilities for the council. The consultants prepared tender documents
and five tenders were received - the lowest tender was accepted.
AERC was employed as project manager for the remediation works and
a relatively short time period of nine weeks was given for the contract
to minimise disruption for the residents.
GARDEN RESTORATION
Prior to works commencing, the local authority and the contractors
held discussions regarding the restoration of the gardens. Detailed
photographic and written records of the contents of the gardens
had to be made before the replanting of the gardens was agreed.
Some residents wanted slight changes to the restored gardens and
this was accepted where it did not increase the overall cost of
restoration. As the works were being carried out in default of a
notice, it was important that all works were reasonable so that
they could not be appealed against when the costs were later reclaimed.
The process of recording the original contents of the gardens and
agreeing the restoration proved to be one of the most contentious
and time consuming elements of the works. The whole process required
close liaison between contractors and residents and eventually,
the residents were asked to sign schedules of agreed works for the
restoration in order to minimise any potential disputes after completion
of the works. The residents were also asked to sign an agreement
to allow the landscapers access for maintenance, which they required
in order to provide the one year guarantee for the survival of the
plants. Maintenance was particularly important as replanting was
in the summer months, which reduced the chance of all plants surviving
- particularly where fairly large trees were being planted.
THE WORK PROGRESSES
As with many remediation projects, additional pockets of contamination
were found as works progressed. This caused problems as authorisation
could only be given for works in accordance with the requirements
of the notice; ie removal of cadmium to abate a statutory nuisance
and not remediation of the site to make it suitable for residential
use, although it was likely to be developed for housing. This meant
that further risk assessments had to be carried out as remediation
progressed and in some cases the contamination was not able to be
removed; eg small pockets of cyanide found along the boundary of
the site. The areas were marked so as to be easily identifiable
should further remediation be required. In other cases, a practical
judgement had to be made, often to the horror of the council's legal
advisors.
RECLAIMING COSTS
Table 1 shows the approximate final cost of the remediation works.
The notice to recover costs was served in February 2000 and was
not appealed. While the value of the land was estimated as ú200,000,
the company had no assets except the land itself and had considerable
debts. Thus, the only possibility of recovering any of the council's
costs was through the sale of the land and even then, it is unlikely
that the costs will be fully recovered. The charge was placed on
the land and formally recorded with the land registry. Although
initially disputed by the mortgage companies, it has now been accepted
that the council's charge takes priority over any other charges
on the land. In the early stages management of the media became
very important as in this case, there was already a neighbouring
contaminated site that had generated a lot of local interest. When
the initial letters were released to the media via the residents
concerned, there was some comment that the council had tried to
"cover it up". In fact, officers were trying to ensure that the
residents were the first to hear any news, before the media. Following
this, at each key stage, news releases were carefully co-ordinated
so that residents, elected members, and the media received written
information and verbal briefings at the same time. There was always
pressure to give time periods for completion of each stage, so it
was important that the time given was generous, as each stage seemed
often to identify further problems that lengthened the process.
A large number of calls were also received from concerned residents
in the general locality, mainly stimulated by scare mongering literature
which was distributed. As a result, newsletters were widely distributed
at key stages by the council, keeping residents informed and providing
contacts for further information. These seemed to be successful
in addressing people's fears and the council received surprisingly
few numbers of calls as a result. The issue of providing the public
with information, while not blighting properties in the area, proved
very difficult. To a certain extent, this had been taken out of
the council's hands by the residents' contact with the media. Undoubtedly,
the properties concerned were blighted and residents who were looking
to move found their lives in limbo until works had been completed.
During remediation work there are nearly always additional areas
or types of contamination which had not been identified in the site
investigation. Hence in writing any notice for decontamination works
it is important to allow enough flexibility to tackle these problems
as they arise while making the requirements specific enough so as
not to leave the notice open to successful appeal. The reinstatement
of gardens is an area which most contractors will have had little
or no experience of, but which will be the most important from the
residents' point of view. The appointment of experienced landscape
gardeners is essential and input from the council's own landscapers
proved valuable in drawing up specifications for reinstatement.
The outstanding impression from completion of such a job is the
amount of officer time involved not just during initial investigations
but throughout the course of the works. The prospect that the new
contaminated land regime may identify a number of sites that need
remediation and involving a larger number of properties would have
an enormous impact on the work of environmental health departments.
If this problem had arisen today it would now be dealt with under
the new contaminated land regime. As contaminant specific guidance
is due to be released it is hoped that it will be easier to justify
the conclusions of any risk assessment, although detailed site specific
assessments would still be needed. However, until this guidance
is released it will be problematic to proceed with any action under
the new legislation. One concern when proceeding with the statutory
nuisance enforcement was that the guidance would be released during
the course of this action, which could then discredit the risk assessment
if it contradicted its conclusions. However, no specific guidance
was forthcoming following discussions with the DETR. In this particular
case the site had been used for electroplating for at least 60 years,
in that time there had been six owners as far as could be established.
The accepted method of disposal and understanding of pollution have
changed greatly in that time. The identification of appropriate
persons, apportioning costs between liability groups and identification
of groups that should be excluded from liability would become extremely
complicated and time consuming under the new regime. The overall
success of this job was helped by teamwork - both internally and
with the contractors involved.The next cases will now be under the
new legislative regime, and the authors look forward to some new
learning experiences in this complex field of work. Joanne Ellis
is Senior Advisor at Applied Environmental Research Ltd (AERC),
an environmental consultancy based near Colchester, Essex. Chas
Bradfield is Environmental Health Manager (Environmental Protection
and Housing) at Wokingham District Council, a unitary authority
in Berkshire. The opinions voiced by the authors in this article
are their own and do not represent the views of their employers.
REFERENCES
1 HM Government, Environmental Protection Act 1990, HMSO.
2 Interdepartmental Committee on the Redevelopment of Contaminated
Land (ICRCL), 59/83: Guidance on the Assessment and Redevelopment
of Contaminated Land, DoE, 1983.
3 The Independent Environmental Health Co-operative, Target and
Intervention Values for Soil and Groundwater in the Netherlands.
4 European Commission, draft Commission regulation setting maximum
limits for certain contaminants in foodstuffs; amending commission
regulation EC 194/97 of 31 January 1997, setting maximum limits
for certain contaminants in food, EC, 1997.
5 DETR, Industry Profile Metal Manufacturing, refining and finishing
works - electroplating and other metal finishing works, HMSO, 1995.
6 Johnson G., Scholes K., Exploring Corporate Strategy 5th Edition,
Prentice Hall Europe, 1999. Readers may be interested in purchasing
the WHO Environmental Health Pamphlet on "Contaminated land", available
from the publications department for ú7.60 each. Tel: 020 7827 58823
or e-mail: publications@chgl.com