Each year, thousands of people die from asbestos-related
illness in the UK alone - each one preventable. Bill Sanderson
comments on the Health and Safety Executive's proposals to
strengthen controls on asbestos in the workplace
With 4,000 people dying each year in the UK from asbestos-related
diseases - a figure predicted to get much worse before it improves
- there is an urgent need to stop a bad situation worsening. Every
one of these deaths is preventable, therefore, most of us with an
involvement with asbestos will be relieved that things are finally
moving on the plans to introduce legislation on the management of
asbestos in buildings.
Four years after the Health and Safety Executive (HSE) first decided
there was a need to raise the profile of the importance of the management
of asbestos in the workplace, an end to the consultation processes
that necessarily precede such major changes is in sight.
DUTY TO MANAGE
The HSE consultation document CD1761 was initially required to
clarify the definition of the duty holder in Regulation 4 of the
draft Control of Asbestos at Work Regulations, since in many buildings
there may be different parties responsible for maintenance of the
building fabric.
CD176 was also needed to review the situation on domestic premises,
since the response to the earlier consultation document CD1592,
which closed consultation on 20 October 2000, indicated that tenanted
domestic premises (particularly local authority housing) should
be placed within the scope of the new Regulation 4. In the end,
however, the legal problems could not be resolved and this will
not be required. The HSE has reserved its position on this topic.
Consultation on CD176 closed on 19 February 2002, so the HSE can
now progress with reviewing the responses and finalising the regulations
to be placed before Parliament. After the statutory three-month
introductory period it is likely to become law - perhaps as early
as January next year.
Even though most local authorities (and EHOs in particular) are
au fait with the bulk of the proposed legislation, the HSE expects
to allow a further 18-month lead-in period for the implementation
of the new Regulation 4 (duty to manage asbestos in the workplace).
This is a generous allowance, especially since the end result was
clear from the HSE's original intentions declared in April 1998.
However, some organisations will still require all the time allowed
in order to be able to comply with this regulation as they have
done little, if any, preparation.
It remains to see how well the duty holders will implement Regulation
4. There is concern that many will feel that once a survey, condition
risk assessment and a register are completed, no further action
is required. The HSE will disabuse them of this opinion very quickly.
It is intended that the new regulations will force the development
of a management plan which keeps asbestos materials in safe condition
and that materials are inspected under a periodic review. It is
also intended that systems should be developed which provide information
for those who need to know about the asbestos present (ie tenants,
staff and visiting contractors).
If it is to be done properly, ensuring that asbestos is not accidentally
or deliberately damaged with the risk of unnecessary exposure to
asbestos for occupants, maintenance staff and others, this is far
more demanding of time and resources.
CD176 includes a new draft Approved Code of Practice (ACoP) on
the proposed new Regulation 4. The HSE is also about to issue further
guidance on the management plan, including the prioritisation assessment
removed from the first drafts of the technical guidance document
MDHS1003. This should ensure that when inspection time comes, whether
visits are made by HSE inspectors or EHOs everybody will be singing
from the same hymn sheet.
ACCREDITATION REQUIREMENT
There are two other new areas where the HSE is also seeking strengthened
controls. First, at the suggestion of the HSE's Committee on Fibre
Measurement (CFM), CD176 has introduced a new requirement for laboratories
undertaking asbestos identification to be accredited by an appropriate
body (ie the United Kingdom Accreditation Scheme) to ISO 17025.
The draft regulation places the responsibility on the user of the
service, not necessarily on the laboratory - this is exactly the
same as the current requirement for laboratories carrying out air
sampling and fibre counting for asbestos.
While it would be preferable for the bulk sampling to be made subject
to accreditation as well as the testing, it is the HSE's view that
it would be unreasonable to require a removal contractor, for example,
finding unexpected asbestos material to have to wait for an accredited
laboratory to arrive to take a single sample.
Some laboratories feel unhappy at analysing samples delivered
to them by unknown sources as there is a serious risk that the sample
provided is not representative of the material at the site. Pipe
insulation in particular, is notoriously heterogeneous (non-uniform)
because of patches, repairs and extensions, or simply because of
its original installation. Nevertheless, this is a normal commercial
arrangement which will certainly continue, so UKAS-accredited laboratories
always issue strict disclaimers regarding the sampling when a certificate
of analysis is issued.
The HSE, however, has a clear commitment to accreditation for sampling
and testing activities where possible and it is probable that this
will eventually be extended to asbestos surveyors. The survey accreditation
(to EN 45004) is now in place and some 30 organisations are already
accredited, but this is a small number compared with what HSE expects
to need in order to complete the survey requirements of the draft
regulation.
It is still perhaps too new to allow it to be included definitively
in the regulations. The proposed individual surveyor certification
schemes are much further behind in development and will not be ready
until later this year.
CLEARANCE TESTING UNDER SCRUTINY
Second, and very much more radical, the HSE is looking at the role
and function of laboratories carrying out clearance testing after
asbestos removal. Current practice dictates that a laboratory will
be called in by the asbestos removal contractor to carry out independent
clearance tests at the completion of the asbestos removal.
The HSE, however, has for some while been less than pleased with
the standards of this clearance testing by the laboratories. A few
years ago, the Bristol region of the HSE surveyed some enclosures
in its area that had been cleared and the enclosures removed. Almost
50 per cent were not satisfactory - visible debris was still present.
To confirm this, the Health and Safety Laboratory (HSL) at Sheffield
last year carried out a survey of around 16 projects, observing
laboratories undertaking clearance inspection and air tests. Worryingly,
even though the laboratories were aware of the attentions of the
executive, they continued to operate at unsatisfactory levels. While
the HSL felt that only two out of 16 projects should have passed,
the laboratories failed only one enclosure - an unacceptable situation.
As a result, the ACoP L28 (Work with asbestos insulation, asbestos
coatings and asbestos insulating board) will make some radical changes
on the clearance process. These changes will be the biggest advance
since the introduction of disturbed air tests in the early 1980s
and are likely to send shockwaves through the industry.
At present, the contractor usually will employ the laboratory to
do the clearance inspection and air test at the end of the contract.
This naturally puts the laboratory in the wrong commercial situation
since it is beholden to the contractor and not to the client whose
interests they should be protecting. L28 will, therefore, make a
much stronger requirement for the laboratory to be responsible directly
to the client and not to the contractor.
FOUR STAGE PROCESS
More importantly, the clearance procedure will now be a four-stage
process:
Stage 1 - a site inspection to ensure the enclosure
is sound, the negative pressure unit running, the decontamination
unit connected to services and in good order, no asbestos debris
outside the enclosure or on the routes from the airlock to the
skip. This is a new requirement although some laboratories do
this as a routine already.
Stage 2 - a visual inspection inside the enclosure as
before, but the HSL wants to see better means of inspecting for
the presence of surface dust and debris, including some form of
"wipe tests" or the use of a torch held at low angle
to detect dust.
Stage 3 - a clearance air test as before, but with more
efficient dust-raising techniques. Brushing surfaces with disposable
brushes will be recommended. Flapping plastic bags, waving clipboards
and PVA spraying of the enclosure surfaces will not be permitted.
Stage 4 - a new requirement for a post-enclosure removal
inspection for debris that may have become trapped within the
folds of the enclosure or underneath the floor sheeting. The enclosure
area cannot be handed back to the client until this inspection
has taken place and a certificate for reoccupation presented.
This must be done by a competent person who is independent of
the contractor.
All of this will have some significant repercussions. There will
clearly be much greater responsibility on the clearance analyst.
This should enhance their professional status and will probably
result in demands for better salaries to reflect their responsibilities.
The HSE is already talking to UKAS about the implications of this
on laboratory accreditation, and it is possible that this would
require an extension to the inspection body accreditation already
in place under EN 45004. This will have a significant financial
impact which will have to be passed on to the clients.
The HSE may even look to proceed to a system where only a certified
analyst can undertake clearances. The level of training and qualification
will undoubtedly be raised significantly.
The amount of time involvement by the analysts will increase substantially,
to include the two new stages - site inspection (stage 1) and the
post clearance site inspection (stage 4). The cost of a clearance
test will therefore increase dramatically - a cost that will also
inevitably be passed on to the client. However, beneficially, the
job should be done right first time and public health will be protected
much better than before. The dangers of asbestos have been known
in the UK for more than 100 years (life insurance premiums in the
very early 1900s were loaded for anybody working within an asbestos
factory) and it is only recently that we have been giving the subject
the attention it demands.
Bill Sanderson works in business development, asbestos and occupational
hygiene in the training division of the Casella Group. Mr Sanderson
is a leading provider of asbestos technical training courses and
is a member of the HSE's Committee on Fibre Measurement (CFM) and
two of its working groups. He has close contact with the HSE and
its current thinking on asbestos.
References
CD176: Revised proposals for amendments to the Control of Asbestos
at Work Regulations and a new supporting Approved Code of Practice.
Available on the web: www.hse.gov.uk/condocs/closed/cd176.htm
CD159: Proposals for amendments to the Control of Asbestos
at Work Regulations 1987 and a new Approved Code of Practice,
and a minor amendment to the Health and Safety (Enforcing Authority)
Regulations 1998. Available on the web: www.hse.gov.uk/condocs/closed/cd159.htm
MDHS100: Surveying, sampling and assessment of asbestos-containing
materials. Available to order from the web: www.hsebooks.co.uk
(ISBN 0 7176 2076X price £18).