|
EHJ
January 2005, pages 16-18
The contaminated land regime has its limits, but it has also produced
success stories. Marie-Claire Kidd visited the former Mirvale tar
distillery in West Yorkshire to find out what happened when this
particular site became "special"
Back in 2001, four closed landfills and two chemical works were
the first six "special sites" designated under the new
contaminated land regime. Among them was the former Mirvale tar
distillery on the banks of the river Calder in West Yorkshire,
where a cocktail of chemicals had been flowing from groundwater
into the river, and which became the first "orphan site" to
be remediated under part IIA of the Environmental Protection Act
1990.
The river bank at the site had been seeping with what looked like
oil for decades, producing a film on the river surface extending
bank-to-bank and for hundreds of metres, and eventually turning
into a grey-black sludge that would stick to vegetation and boats.
There was a large plume of volatile organic compounds, phenols,
pesticides and herbicides originating from the site, clearly visible
on a calm day and producing a distinctive odour. Only when the
slick hit a weir 800m downstream did it disappear, unlike the smell.
The culprit was highly toxic creosote, both neat and in various
states of decomposition, which is present in large quantities in
the land at the former works. It leaches into soil and groundwater,
as creosote easily does, and was flowing freely into the river.
It was the police, on a helicopter flight above the site, who
first realised the extent of the pollution. They recorded the slick
on video and notified the Environment Agency, sparking off an investigation,
which led to the eventual determination of the site as contaminated
under part IIA, and its successful remediation.
"I've seen the video and it looked quite horrendous," says
John Barber, contaminated land officer at the agency's Leeds office. "The
police had the perfect viewpoint to see the extent of the pollution.
It must have been a day when the river was very flat. They thought
there'd been a catastrophic incident and flagged it up to the agency,
in fact it had been going on for decades."
Kirklees MDC determined the site as contaminated under part IIA
in April 2001, just a year after the new regime was enforced. The
contaminant was named as creosote, the pathway was the made ground
and alluvial sands and gravels beneath the site and the receptor
was groundwater and ultimately the river. Because the contamination
affected controlled waters the area was designated a "special
site" and immediately fell into the hands of the Environment
Agency, which had by then been investigating the site for years.
There is anecdotal evidence that there were works on the site
as early as 1890 but the first detailed records show Mirvale was
taken over for munitions manufacture during the First World War.
In the 1950s it became a chemical plant, and the scene of a massive
fire in the 1970s. The works became known as Mitchell Cotts in
1976, and went through two changes of ownership until Dow Chemical
acquired it as part of Ascot plc in June 2000, just two months
after the site was determined.
Mitchell Cotts still operates on part of the site, where it manufactures
pyrethroids, active pharmaceutical ingredients and intermediates.
These include cypermethrin, an insecticide used by farmers to protect
crops such as cotton, cereals, orchard fruits and vegetables, permethrin,
used in pet collars to kill fleas, permethrin BPC, used in headlice
shampoos and scabies creams, and travaprost/prostaglandin, for
use in the prescribed drug travatan, which is sold for the treatment
of glaucoma. The remainder, which also belongs to Mitchell Cotts
and which is thought to be the most contaminated section, is derelict.
But it was during the intervening period, when the site was a
tar distillery that the most serious contamination seems to have
occurred. Large storage tanks, of about 40,000 gallons capacity,
appear to have been emptied into the ground, probably towards the
end of the tar distillery's life or on its conversion to a chemical
works.
"The original polluter was no longer in existence. The land
had been bought from them by Mitchell Cotts," says Mr Barber. "There's
nobody on site that was there when the contamination occurred.
"It was in the fifties or even earlier when these tanks were
last used," he continues. "In the fifties one was partially
demolished. It's probable that was when the contamination occurred.
It's assumed they contained creosote."
Mr Barber says organic chemicals are difficult to identify. "They're
not just a single simple chemical, they're a mixture of several
hundred different chemicals. It could take several years to migrate
into the river, and when it migrates its character changes, some
parts of the mixture stick to soil, some dissolve, some evaporate
into the air, but it still smelt like creosote."
On designation of the area as a special site, the agency undertook
further investigations, into both "appropriate people" and
options as to the site's remediation. Under the regime, it could
seek to recover some but not all of its remediation costs from
the landowner, Mitchell Cotts, which as the occupier was deemed
a "class B" company and thus liable for part of the clean
up operation.
After negotiations between the agency and the company it was agreed
that the costs would be split 50-50. The agency would shoulder
the £500,000 capital works, thanks to a Defra supplementary
credit approval grant, and the company would pay ongoing operational,
maintenance and monitoring costs for approximately 20 years - also
expected to reach the value of about £500,000.
Following year-long negotiations with Railtrack, which owns the
mainline viaduct under which works had to be undertaken, the agency
was able to install a cut-off wall and equipment to pump and store
the creosote. The works were completed on 9 July 2002.
The interception system, designed to reduce the amount of non-aqueous
phased liquid or NAPL entering the river, involves collecting the
creosote from a horizontal pipe behind a sheet pile dam of some
150m in length located next to the river upstream of the slick.
NAPL is lighter than water and floats on the surface of groundwater,
allowing it to be skimmed off the surface. The trench is equipped
with underground skimmer pumps, maintainable via a series of manholes
along the banks of the Calder, which pump the creosote via a pipeline
to a holding tank on the Mitchell Cotts site. The creosote collected
in the tank is disposed off site.
The scheme does not deal with the dissolved part of the contamination
plume, which is addressed by dilution in the river - a method that
would not be considered ideal by the agency - or the volatile organic
compounds.
The results have been remarkable. The residents of Mirfield used
to presume that Mitchell Cotts was responsible for the unpleasant
smell that occasionally wafted over the town. The clean-up operation
has proved them wrong - the chemical works is still there but the
smell isn't.
"The amount of creosote that now enters the river has dramatically
reduced," says Phil Waine, Environment Agency technical advisor. "Although
you get the occasional blob coming up to the surface, you don't
get the huge outpourings any more and the smell has gone. Since
working on the site, we've regraded the soil and put down grass
seed. A lot of self-seeding flowers have grown there and it now
looks quite pretty."
Mitchell Cotts is continuing to monitor the scheme in case any
more treatment is needed, and is required to submit an annual report
to the Environment Agency. Its second annual report is expected
in February.
"The main thing was that there was no creosote or creosote
products visible on the river and it's achieved that," says
Adrienne Goodwin, Dow Chemicals' UK regulatory affairs leader. "There
hasn't been since about three weeks after the scheme was installed,
which you'd expect because the scheme's got to settle."
While the Environment Agency monitors the river for levels of
creosote, the firm checks the equipment on a weekly basis and it
employs consultants TES Bretby to sample groundwater across the
site every quarter.
"The contamination could divert and we want to make sure
that it doesn't. It doesn't look like it is, it's been superbly
engineered. It's almost like the advert - it does what it says
on the tin," says Ms Goodwin.
|